January 2017 - July 2017

  • Create rough draft of documents
  • Identify risks
  • Attend HLC National Conference (core team)

August 2017

  • Complete initial draft
  • Identify steering committee members
  • Launch HLC website to the public

September 2017

  • Kick-off Steering Committee
  • Launch university-wide communication plan
  • Attend UC governance meetings

October 2017

  • Revise drafts
  • Attend UC governance meetings
  • Collect evidence to support claims
  • Identify sources

November 2017

  • Attend governance meetings for additional input  and feedback

December 2017

  • Creation of final report by the Steering Committee

 

 

January 2018

  • Continue finalizing working draft
  • Conduct interviews
  • Confirm, fact check, and validate draft document and supplementing materials
  • Continue steering committee meetings

February 2018

March 2018

  • Collect public comments and feedback
  • Revise draft, incorporating public feedback
  • Compile any additional evidence or supporting materials

April 2018

  • Finalize draft
  • Load evidence into HLC system

May 2018

  • All UC HLC documents uploaded into HLC system

August 2018

  • August 25: Public comment period closes

September 2018

  • September 24-26: HLC Site Visit